Location: Zhejiang Province, China
Mission: 100% inspection of pre-wired electrical panels.
Context: A set of 50 pre-wired electrical panels were ready to be shipped. Our customer missioned our electrical engineers to verify the wiring of all 50 panels and test their functions.
Results:
The report was submitted with full detail: load specifications, applied current and voltage. We recorded and measured the fault current, its value to trigger circuit breakers. Short film of the tests were also submitted. We take into account different earthing / ground arrangement TT, TN, IT.